TeraWulf 董事长兼首席执行官 Paul Prager 在一份声明中表示:“当我们在 2 月份宣布收购 Justified Data 园区时,我们告诉投资者,我们预计将在 2026 年第二季度末左右获得主要客户的承诺。” “今天宣布的时间反映了最终文件和惯例交易流程的完成,我们很自豪地宣布与 Anthropic 建立这一具有里程碑意义的合作伙伴关系。”
每日简报时事通讯
每天从当前的热门新闻报道以及原创专题、播客、视频等开始。
In brief
TeraWulf signed a 20-year lease with Anthropic for a ~401 MW AI data center campus in Hawesville, Kentucky, expected to generate ~$19 billion in revenue.
The firm is also selling its 50.1% stake in the Abernathy Joint Venture to a group led by partner Fluidstack, cashing out its ~$450 million investment at a premium.
Bitcoin mining stocks are broadly up big early Monday, led by TeraWulf and IREN.
Bitcoin miner TeraWulf is placing a major bet on artificial intelligence, striking a 20-year lease with Anthropic that the company says could bring in roughly $19 billion in revenue while shedding part of its stake in a separate Texas data center project.
Shares in TeraWulf (WULF) spiked following the announcement, recently trading at $24.05—a nearly 14% jump on the day.
However, the move appears to have boosted confidence across a slate of Bitcoin mining firms that are increasingly leaning into AI compute, with IREN shares up more than 13%, Hut 8 up 12%, and Cipher Digital rising 11%. Keel Infrastructure (formerly Bitfarms), which rebranded and exited Bitcoin mining entirely to focus on AI, is also up 10% on the day.
Under the deal announced Monday, Anthropic will occupy a purpose-built campus at TeraWulf's Justified Data site in Hawesville, Ky., a facility expected to eventually support about 401 megawatts of computing capacity. The first phase is slated to come online in the second half of 2027, with the site reaching full capacity by early 2028. TeraWulf said the lease is expected to be supported by an investment-grade credit rating.
The Maryland-based company, traditionally known for Bitcoin mining, has been pivoting toward AI infrastructure as demand for computing power used to train large language models has surged. Anthropic, the AI company behind the Claude chatbot, is one of several major players racing to secure long-term power and data center capacity as it scales up its models.
In a separate move, TeraWulf agreed to sell its 50.1% stake in the Abernathy Joint Venture—a Texas data center project developed with partner Fluidstack—to an investor group led by Fluidstack. The transaction monetizes TeraWulf's roughly $450 million investment at a premium to invested capital. Fluidstack will take over leadership of the project going forward.
“When we announced the Justified Data campus acquisition in February, we told investors that we expected to secure a major customer commitment by around the end of the second quarter of 2026,” said TeraWulf Chairman and CEO Paul Prager, in a statement. “The timing of today's announcement reflects the completion of final documentation and customary transaction processes, and we are proud to announce this landmark partnership with Anthropic.”